| '''Author(s)''' || style="background:Lavender"|''Realgruen landscape architects office''
| '''Author(s)''' || style="background:Lavender"|''Asma Sahboon''
|-
|-
| '''Completion''' || style="background:Lavender"|''Competition: 2007 - Drafting, 2008 to 2011: Construction''   
| '''Completion''' || style="background:Lavender"|''Competition: 2007 - Drafting, 2007 to 2010: Construction''   
|-
|-
| '''Client''' || style="background:Lavender"|''Aurelis Real Estore Gmbh&CO.KG''
| '''Client''' || style="background:Lavender"|''Aurelis Real Estore Gmbh&CO.KG''
Line 25: Line 25:
|}
|}


=== Rationale: Introdaction
 
 
=== Introduction ===
Along the central axis of Munich between main station and train station
Pasing created on former railway land new urban quarters between the growing areas, "On Deer Garden" in the east and the
Nymphenburg castle district in the west is a large central public. Green space is produced through the north of the historic park "Deer Garden" and in the south of the planned rail habitat accompanying band, the "Pioneer Park". The frame of Green" is the deer yard expansion area of approximately 5.2 hectares with a further concurrent planning phase more concrete.
The concept for the development was to mak a conection between Deer Garden(Fruit Garden) and the Pioneer Park, and also it has been provided with the facilities for all ages. Inter alia creates a Youth gaming device, with opportunities for noisy game. A major focus of the challenge lies not only in the Refinement of different functional areas within the planning area, but also in the definition of the transitions to the adjacent Planning areas. Another issue is the residential areas which have special requirements of green and open space design the City of Munich and which will use the new open green space.


Along the central axis of Munich between main station and train station Pasing created on former railway land new urban quarters between the growing areas, "On Deer Garden" in the east and the Nymphenburg castle district in the west is a large central public. Green space is produced through the north of the historic park "Deer Garden" and in the south of the planned rail habitat accompanying band, the "Pioneer Park". The frame of Green" is the deer yard expansion area of approximately 5.2 hectares with a further concurrent planning phase more concrete. The concept for the development was to make a connection between Deer Garden (Fruit Garden) and the Pioneer Park, and also it has been provided with the facilities for all ages. Inter alia creates a Youth gaming device, with opportunities for noisy game. A major focus of the challenge lies not only in the Refinement of different functional areas within the planning area, but also in the definition of the transitions to the adjacent Planning areas. Another issue is the residential areas which have special requirements of green and open space design the City of Munich which will use the new open green space.


===Why is this case interesting? ===  
===Why is this case interesting? ===  
This case is an exapmle for a larg professional participation project and also the first price project in Munich City development palnning competition 2007.  
This case is an example for a large public participation and professional project and also the first price project in Munich City development planning competition 2007.


=== Author's personal background ===
=== Author's personal background ===


Klaus D. New man -
Asma Sahboon
1976-1983Study of the landscape architecture at the TU Munich, conclusion Dipl. Ing.TU
   
1996-2002Bachelor of Architecture&Urban design Engineer.Faculty of Engineering - Elfateh University - Libya, .
    
    
1984-1986Collaboration with Dr. Werner Nohl, research project MAB – landscape aesthetics self-employed
2002-2008Employed as an Architect in the Ministry of Housing& Urban development.
handlly as a landscape architect foundation office actually green - office for free space planning and
landscape architecture
2007-2008Assistant in the Elfateh University-Libya.
 
1992-2000 Professor at the HSR, university Rapperswil, CH
 
01/1999 partnership with wolf D.Auch  Landscape architects&actually green
 
Member in the architect chamber Bavaria member of the BDLA, alliance of German landscape architects
competition juries
 
 
Wolf D.Auch -
1984-1989Study of the landscape architecture at the Technical College Wiesbaden, conclusion Dipl.  Ing.  
Technical College


1989-1993: Activity as a landscape architect in the studio star and partner in Zurich self-employed handlly
2009: Student in International Master of Landscape architecture- Germany.
as a landscape architect
 
01/1993 collaboration with prof. Klaus D.  New man office actually green, Munich
 
01/1999 partnership with Klaus D. Landscape architects actually green new man
 
Member in the architect chamber Bavaria member of the German of work alliance competition juries


=== Process Biography Scheme ===
=== Process Biography Scheme ===


''Please add the scheme of your project's process biography here, below you see an example. Please replace this file with your own.''
[[Image:Deer Garden by Asma Sa.jpg|none|800px|Process biography example]]
 
 
 


=== Who initiated the project and why? ===
=== Who initiated the project and why? ===


The Ministry of Transport and Building & Urban  Development  department have been initiated this project.The idea was to make a connection and good integration between different functional areas such like deer garden as a historical garden and Pioneer park and new residential areas, that  have special requirements of green and open space with high quality.


=== When was public participation most intensive?  ===
=== When was public participation most intensive?  ===
 
The public participation was most intensive in the development deer garden zone (preparatory stage phase) and were only the students &professional participations in planning and implementation phases.


=== Which participation tools have been applied? ===
=== Which participation tools have been applied? ===
They used Co. Knowing (to collecting information through the surveying ) -Co. Planning (to adding the extra requirement after the competition) and also Co. Discussion (to get good solution to the development park) and Co. Implementation (they have been made small fest in the construction phase)
==== On which level of participation? ====


=== Which stakeholders have been involved?  ===  
=== Which stakeholders have been involved?  ===
Citizens-Students from TUM landscape architecture department-Landscape architects-Gardeners-Construction engineers have been involved in this project.


=== Have there been any festivities in order to involve the public?  ===
=== Have there been any festivities in order to involve the public?  ===
There were an exhibition in competition phase then small fest in the construction phase and the opening fest will be in May 2010.


=== Who made the major decisions and when?  ===
=== Who made the major decisions and when?  ===


[[#toc|'''Back to top''']]
 
Prof.Neuman and Mr.Eng.Auch have been made the most decisions in the competition phase and also in preparatory stage phase.  In this case demanded the owner to addition another requirement in the project but the major decisions have been made by Ministry of Transport and Building & Urban  Development  department.


=== Image Gallery ===
=== Image Gallery ===
Line 95: Line 74:


<gallery caption=" " widths="150px" heights="150px" perrow="3">
<gallery caption=" " widths="150px" heights="150px" perrow="3">
[[Image:Example Luftbild hirschgarten2.jpg.jpg]]
Image:Hirschgarten.jpg|Google map photo
[[Image:ExampleKran6.JPG.jpg]]
Image:Luftbild hirschgarten2.jpg‎|Aerial photo
[[Image:Example11 1DSC 0094.jpg.jpg]]
Image:08 DSC 0069.jpg‎|Site over view
[[Image:Example 06_CIMG0370_Kopie.jpg‎ .jpg]]
Image:11 1DSC 0094.jpg|Over view through construction phase
[[Image:Example 12 1DSC 0281.jpg.jpg]]
Image:06_CIMG0370_Kopie.jpg‎| Climb wall through construction
[[Image:Example 10 P1030322.jpg.jpg]]
Image:12 1DSC 0281.jpg|Football place
Image:12 DSC 0294.jpg|Basketball place
Image:1223.jpg|Playing areas
Image:222.jpg|Seating areas
</gallery>
</gallery>



Latest revision as of 14:11, 26 February 2010

by Asma

back to Project Biography List

Name Hirschgarten erweiterung (Deer garden expansion)"
Place Munich
Country Germany
Author(s) Asma Sahboon
Completion Competition: 2007 - Drafting, 2007 to 2010: Construction
Client Aurelis Real Estore Gmbh&CO.KG
Project costs 6.46 Mio Euro
12 DSC 0293.JPG


Introduction

Along the central axis of Munich between main station and train station Pasing created on former railway land new urban quarters between the growing areas, "On Deer Garden" in the east and the Nymphenburg castle district in the west is a large central public. Green space is produced through the north of the historic park "Deer Garden" and in the south of the planned rail habitat accompanying band, the "Pioneer Park". The frame of Green" is the deer yard expansion area of approximately 5.2 hectares with a further concurrent planning phase more concrete. The concept for the development was to make a connection between Deer Garden (Fruit Garden) and the Pioneer Park, and also it has been provided with the facilities for all ages. Inter alia creates a Youth gaming device, with opportunities for noisy game. A major focus of the challenge lies not only in the Refinement of different functional areas within the planning area, but also in the definition of the transitions to the adjacent Planning areas. Another issue is the residential areas which have special requirements of green and open space design the City of Munich which will use the new open green space.

Why is this case interesting?

This case is an example for a large public participation and professional project and also the first price project in Munich City development planning competition 2007.

Author's personal background

Asma Sahboon

1996-2002: Bachelor of Architecture&Urban design Engineer.Faculty of Engineering - Elfateh University - Libya, .

2002-2008: Employed as an Architect in the Ministry of Housing& Urban development.

2007-2008: Assistant in the Elfateh University-Libya.

2009: Student in International Master of Landscape architecture- Germany.

Process Biography Scheme

Process biography example

Who initiated the project and why?

The Ministry of Transport and Building & Urban Development department have been initiated this project.The idea was to make a connection and good integration between different functional areas such like deer garden as a historical garden and Pioneer park and new residential areas, that have special requirements of green and open space with high quality.

When was public participation most intensive?

The public participation was most intensive in the development deer garden zone (preparatory stage phase) and were only the students &professional participations in planning and implementation phases.

Which participation tools have been applied?

They used Co. Knowing (to collecting information through the surveying ) -Co. Planning (to adding the extra requirement after the competition) and also Co. Discussion (to get good solution to the development park) and Co. Implementation (they have been made small fest in the construction phase)

Which stakeholders have been involved?

Citizens-Students from TUM landscape architecture department-Landscape architects-Gardeners-Construction engineers have been involved in this project.

Have there been any festivities in order to involve the public?

There were an exhibition in competition phase then small fest in the construction phase and the opening fest will be in May 2010.

Who made the major decisions and when?

Prof.Neuman and Mr.Eng.Auch have been made the most decisions in the competition phase and also in preparatory stage phase. In this case demanded the owner to addition another requirement in the project but the major decisions have been made by Ministry of Transport and Building & Urban Development department.

Image Gallery

Back to top

References


realgrün Landschaftsarchitekten Büro - Prof.Klaus-D. Neumann - Wolf D. Auch - Mariahilfstrasse 6- 81541 München